Angela Cina
La Crosse Tribune, Wis.
(TNS)
After a three-year process, the Viroqua Fire Department is getting closer to moving into a new station that will offer more functionality and safety for its members.
The 26,000-square-foot fire station was constructed on city-owned property located on Nelson Parkway, just north of the Wild West Days grounds. The process, which began in 2022, started with Keller, Inc. and the building concept and working through the grant process with Sen. Tammy Baldwin’s office. Baldwin’s office helped secure a $5.2 million USDA Community Facilities Grant.
Fire Chief Chad Buros said crews began moving dirt for the construction project at the end of July 2024. A groundbreaking ceremony was held June 26, 2024.
A work in progress
The new Viroqua Fire Station is located on Nelson Parkway. Construction could possibly be wrapped up by the end of August, with a soft move-in possibly the first week of September.
Buros said there were no major delays during the construction. “There are always little things; Keller did a good job changing things up, so we didn’t lose time. A few times, rain showers slowed things down when we first moved dirt last fall. They shifted gears to do something else … the project never stopped.”
In an interview on Aug. 8, Buros said crews are now doing the finishing touches on such things as working on some of the electrical and plumbing, touching up paint and working on the parking lot. He said the parking lot work “is a big step” for the project.
In a week-and-a-half the department will move the breathing air compressor for firefighters’ air packs and the gear washer from the current station on East Broadway Street and reinstall them at the new station, Buros said.
Once such things as HVAC and the generator are set up and ready to go, Buros said there will be training over the next few weeks.
The fire chief said construction could possibly be wrapped up by the end of August, with a soft move-in possibly the first week of September. “We’d move the emergency operations first, including fire trucks and bunker gear.” The “office-type stuff,” he said, would be moved throughout September.
Buros said the expectation is for the new station to be 100% functional mid to late September; however, that depends on weather and call volumes. “That’s our timeline of hopes.”
Buros said the fire department doesn’t have to rush to move out of the current station. “That’s a good thing. We don’t want to rush.”
Parking lot work
Crews work on the parking lot at the new Viroqua Fire Station, Friday, Aug. 8.
There’s a preliminary plan to have an open house the first of October. “We want the public to see what has happened,” Buros said. “Our house is their house.” He noted the event would have everybody who was involved with the project, including the city council, representatives from the three townships – Franklin, Jefferson and Viroqua – who partnered with the city, and representatives from Baldwin’s office.
The current Viroqua Fire Station, located at 702 E. Broadway St., is about 12,000 square feet and was originally a beer distributor warehouse. The fire department moved there in the early to mid-1990s and up until about four years ago they shared the building with the Vi