Construction of a new fire station for the Julian Cuyamaca Fire Protection District is well under way. Project superintendent Mike Prida of Southwest Construction Services of Lakeside is pleased with the progress so far and projects a completion date by the end of January 2017 — especially if the weather holds up.
The structural work for the occupied building of the fire station is completely done, with just the interior finishing and painting remaining. The septic system is completed and has been signed off. Caltrans has hydroseeded the roadside entrance to the site and was on schedule to finish the asphalt work by the end of October.
By the time the apparatus building is delivered mid- to late November, he will have the concrete foundation poured, the asphalt done, the site hydroseeded and a sprinkler system installed. Once the building arrives, it should take another three to four weeks to build interior framing, create work areas, do finish work and paint.
Even though the occupied building will be ready in November, building codes will not allow anyone to move into the building until every aspect of the project is completed and has been approved.
"We would have had the project finished in time for Thanksgiving dinner if the building department hadn't held up the apparatus building permit so long," Prida said.
Nevertheless, he is thrilled that the construction should all be done before the winter rains start. That will help keep mud out of the project and maintain clean working conditions, as well prevent costly delays.
A break-in mid-October that resulted in the theft of a computer, iPhone, calculator and chop saw for cutting metal caused another minor setback.
The incident, which was reported to the San Diego County Sheriff's Department, prompted the construction company to install an alarm and security system at the site.
The estimated completion cost of the station is $2.3 million, close to original projections, with only a few unforeseen costs. With a $1.5 million loan and $620,000 in the bank, the JCFPD Board voted to earmark $250,000 to cover any shortfall between now and completion of the station.
Fire Chief Rick Marinelli is hoping not to have to use all of the earmarked funds. The Julian Fireplugs are working to secure donations to furnish the building with office equipment and beds, while the Julian Volunteer Firefighter Association is committed to funding the purchase of new wardrobe closets and nightstands.