Bids to build a new $14.5 million fire station for the Waconia (MN) Fire Department were approved at a recent city council meeting and the new facility is expected to open in the summer of 2024, according to a report published by Sun Patriot Newspapers.
The city got 125 bids for 27 work scopes that are all part of the over all project, according to the report, that added the cost of the fire station is far more than the original estimate of $10 to $12 million.
A consultant for the project said a tight construction market, inflation and the difficulties getting building materials were all factors in the increased cost, according to the report. It was also reported that because of lead times for getting materials, construction won’t begin until next summer and will take about 11 months to complete.